Alright Folks, here we go on the weekly update
Happy to see some movement on the Build of last year is almost all caught up (14 out of 961 pending, 98.5% complete)
Overall numbers from last week (Pretty good week) with overall completion rates
6 more orders added
23 Built - Overall 92.4% complete total
15 Delivered - Overall 66.3% complete total
More metrics/analysis for the data freaks (completion rates with qtys pending)
2021 - (14 out of 961 pending Build, 98.5% complete), delivery is at 88.4% (111 out of 961 waiting for shipping)
Q2-May and June of 2021 are 100% built, delivery is at 97.5% (5 out of 198 waiting for shipping)
Q3-July, Aug and Sep of 2021 are almost 100%(99.5% to be exact) Built (only shy 2 out of 375), and delivery is at 97.9% (8 out of 375 waiting for shipping)
Q4-Oct, Nov and Dec of 2021 Build is at 96.9% (12 out of 388 pending), Delivery starts to rear its ugly head, is at 74.7% (98 out of 388 waiting for shipping)
2022 - (97 out of 502 pending Build, 80.7% complete), delivery is at 23.9% (382 out of 502 waiting for shipping)
Q1-Jan, Feb and March of 2022, Build is at 90.4% (38 out of 406 pending), Delivery continues with challenges, 29.3% (287 out of 403 waiting for shipping)
Q2-April, May and June of 2022, Build is at 39.6% (58 out of 96 pending), Delivery is at 0.01% (95 out of 96 waiting for shipping)
Let me know if any other metrics should/could be evaluated.
View attachment 40292